Please be advised of the closure of James Street at County Road 43 beginning Monday, March 10 until Monday, March 17, 2025. This closure is necessary to facilitate the final installation and commissioning of
the new 300mm watermain installed along the south side of County Road 43. Access to Ultramar Gas Station will be maintained.
This work is part of the County Road 43 Widening Project. For more information on this project, visit the UCLG's project website at: www.countyroad43expansion.com
Or contact:
Alexander Oliveira (Contract Administrator):
Stan Skeggs (Project Manager)
Bill Guy, United Counties of Leeds and Grenville: