The Municipality of North Grenville has initiated a Master Planning process in accordance with Approach 1 of the Municipal Engineers Association (MEA) Class Environmental Assessment (Class EA) to undertake an update to the Water and Wastewater Master Plan that was prepared in 2015.
The Master Plan will identify and assess options to improve the ability of North Grenville’s water and wastewater systems to accommodate the current and future population within the Municipality. This Study is being conducted according to the requirements of Approach 1 of a Master Plan under the Ontario Municipal Class Environmental Assessment process (October 2000, as amended in 2015 and 2023).
Public and agency consultation is a key part of the Master Plan process. Your input will help identify preferred solutions(s) that will support future growth and development.
Who's listening
Timeline
Notice of Commencement
August 2024
August 2024
Phase 1 (Review of Existing Conditions)
October 2024
Phase 2 (Development and Evaluation of Servicing Alternatives)
December 2024
December 2024
Public Information Centre
February 2025